SOP FOR MELTING POINT APPRATUS | STANDARD OPERATING PROCEDURE FOR CLEANING, OPERATION & CALIBRATION OF MELTING POINT APPRATUS

 1.0            OBJECTIVE

To lay down the procedure for operation of Melting Point Apparatus

2.0              SCOPE

This SOP shall be applicable to the Melting Point apparatus used in QC Dept.

3.0              RESPONSIBILITY

3.1              Chemist QC and above shall be responsible for the preparation and execution of this SOP

3.2              Sr. Chemist QC & above and QA Head shall be responsible for the checking and approval of this SOP.

4.0              ACCOUNTABILITY

Head QC

5.0              PROCEDURE

5.1              Cleaning

 

5.1.1        Ensure that power supply to the Melting Point apparatus is switched ‘OFF’ before cleaning and plug shall be removed from the socket.

5.1.2        Melting Point apparatus shall be kept on a clean table/platform.

5.1.3        Platform of Melting Point apparatus shall be wiped with a dry lint the free cloth on a daily basis so that there will be no dust particles on the Melting Point apparatus

5.2              Operation

5.2.1        Ensure that the thermometer shall be kept in the bigger groove provided on the top panel.

5.2.2        Ensure that the capillary tube filled with sample shall be keep in any of the three grooves provided on the top panel.

5.2.3        Ensure that the instrument shall be connected to the mains and switch is “ON”.

5.2.4        Ensure that the Toggle switch shall be “ON” and the red lamp glows.

5.2.5   Ensure for the adjustment of Toggle “HEATER LOW / HIGH” switch as per the desired temperature (up to 150 o C toggle at “LOW”)

5.2.6         Ensure that the “INCREASE TEMPERATURE” knob shall be rotated in the clockwise direction to set the temperature.

5.2.7        Ensure that the temperature shall be noted at which the sample starts melting and ultimately melts completely i.e.  Melting point and melting range respectively.

5.2.8        Ensure that Toggle switch shall be “OFF” after completion of analysis.

5.2.9         Ensure that the mains Switch shall be “OFF”.

5.2.10    Ensure that the thermometer and capillary tube shall be taken out from the grooves.

5.2.11    Calibration Procedure

Calibration of Melting Point apparatus shall be done by external party on annual frequency

 

6.0              REFERENCES

Not Applicable

7.0              ANNEXURE

Not Applicable

8.0              ABBREVIATIONS

SOP         :           Standards Operating Procedure

QC           :           Quality Control

HOD        :           Head of the Department

QA           :           Quality Assurance

QCD        :           Quality Control Department

QAD        :           Quality Assurance Department

            EQP         :            Equipment
SHARE

Owner

Hi. I’m Writer of Researchsop.com. ’ ’ Please share these SOPs to all concern pharma people for their development. I like to fullfill the need of curious people. These things inspire me to make things looks better.

  • Image
  • Image
  • Image
  • Image
  • Image
    Blogger Comment
    Facebook Comment

0 comments:

Post a Comment