1.0
OBJECTIVE
To lay
down the procedure for cleaning, operation &
calibration of hot air oven.
2.0
SCOPE
This
SOP shall be applicable for cleaning, operation &
calibration of Vaccum oven
in Chemistry Lab.
3.0
RESPONSIBILITY
3.1
Chemist and above shall be responsible for
the preparation and execution of this SOP
3.2
QC & QA Head shall be responsible for the checking and approval of this
SOP.
4.0
ACCOUNTABILITY
Head QC
5.0
PROCEDURE
5.1
Cleaning
5.1.1 Ensure that the power supply to the Vaccum oven is switched ‘OFF’ before
cleaning and plug shall be removed from the socket.
5.1.2 All surfaces, walls, top, bottom, and trays of the Vaccum oven shall be wiped with a dry lint of the free cloth on a daily basis so that there will be no dust particles in the Vaccum oven.
5.1.3 All the parts and
outer surface of the Vaccum oven shall be wiped with wet lint a free cloth soaked in purified water, on weekly basis.
5.2
Operation
5.1.4
Ensure that the instrument shall be connect to the main and
switch “ON”.
5.1.5
Ensure that the Toggle switch of the instrument shall be “ON”.
5.1.6
Ensure that the bulb (red) “LINE INDICATOR” shall be glows.
5.1.7
Ensure that the “THERMOSTAT” knob shall be set at specified
temperature.
5.1.8
Ensure that bulb (green) “THERMOSTAT INDICATOR” shall be set
to stop glowing when the specified temperature is attained.
5.1.9
Ensure for the electronic temperature controller displays the
chamber temperature.
5.1.10 Five knobs shall be unscrewed to open the door.
5.1.11 The sample shall be keep on the tray inside
the oven.
5.1.12 After that the door shall be
close and ensure the tightening of the knobs.
5.1.13 Ensure that the vacuum pump
shall be connected to the vacuum nozzle (on top panel ) of the oven.
5.1.14 The vacuum releasing knob shall
be open (on top panel) of the oven to apply the vacuum.
5.1.15 The vacuum releasing knob shall be close as
soon as the vaccum gauge reads the specified vacuum.
5.1.16 The sample shall be dry under vacuum at
specified temperature for specified time.
5.1.17 Ensure for the vacuum gauge
reads zero and the vacuum releasing knob shall be open after completing the drying
5.1.18 After completing dry the five
knobs shall be unscrewed to open the door.
5.1.19 The sample shall be take out from the oven
5.1.20 Ensure
for the cycle is over and oven shall be switch “OFF” the main and the power supply.
5.1.21 Calibration of the instrument:
Calibration
of Vaccum oven shall be done by the external party on annual frequency.
6.0 REFERENCES
Not Applicable
7.0 ANNEXURE
Not Applicable
8.0 ABBREVIATIONS
SOP : Standards Operating Procedure
QC : Quality Control
HOD : Head of the Department
QA : Quality Assurance
QCD : Quality Control Department
QAD : Quality Assurance Department
EQP : Equipment