1. Purpose: To define a system in the organization when the test results are found non-conforming.
2. Scope: This procedure is applicable to all tests being conducted in the laboratory.
3. Responsibility: Technical Manager is responsible to implement this procedure.
4. Procedure:
4.1 The non-conforming test results may be identified at three stages-
a) At the time of testing
b) After completing the test, the test results are not reported to the customers.
c) Non-conformity is detected when the test results are reported to the customers
4.2 In situation (a), the testing is immediately stopped by the quality or technical manager, and resumption of tests is being done after authorization of the technical or quality manager.
4.3 The evaluation of the significance of the nonconforming work is made and action is taken accordingly.
4.4 In situation (b), the samples are re-tested and revised test data are recorded, appropriate remarks are given in the old test data.
4.5 In situation (c) Customer is informed about the nonconforming testing and an amended report is sent to the customer in case there is a writing mistake.
4.6 Technical Manager is authorized for resumption of work
5. References: Nil
CHANGE HISTORY
Sr.No. | Date of change | Revision no. of old document | Date of old document | Revision no. of Revised document | Date of Revised document | Nature of change (addition/deletion) |
END OF THE DOCUMENT
***********************************************************************************
You Also Like to See This:
2. PTL /QSP/02 Procedure for Document & Data Control
3. PTL /QSP/03 Procedure for Purchasing, Services, and Supplies
4. PTL /QSP/04 Procedure for Service to the Customer
5. PTL /QSP/05 Procedure for Customer Complaints
6. PTL QSP/06 Procedure for Control of Non-Conforming Testing.
7. PTL /QSP/07 Procedure for Improvement
8. PTL /QSP/08 Procedure for Corrective Action
9. PTL /QSP/09 Procedure for Preventive Action
10. PTL /QSP/10 Procedure for Control of Records
11. PTL /QSP/11 Procedure for Internal Audit
12. PTL /QSP/12 Procedure for Management Review
13. PTL /QSP/13 Procedure for Training
14. PTL /QSP/14 Procedure for Housekeeping
15. PTL /QSP/15 Procedure for Estimation of Uncertainty of measurement
16. PTL /QSP/16 Procedure for Equipment
17. PTL /QSP/17 Procedure for Measurement Traceability and Calibration
18. PTL /QSP/18 Procedure for Sampling
19. PTL /QSP/19 Procedure for Handling of Test and Calibration Items
20. PTL /QSP/20 Procedure for Assuring the Quality of Test
21. PTL /QSP/21 Procedure for Reporting of Results
22. PTL/QSP/22 Procedure for use of NABL Symbol
3. PTL /QSP/03 Procedure for Purchasing, Services, and Supplies
4. PTL /QSP/04 Procedure for Service to the Customer
5. PTL /QSP/05 Procedure for Customer Complaints
6. PTL QSP/06 Procedure for Control of Non-Conforming Testing.
7. PTL /QSP/07 Procedure for Improvement
8. PTL /QSP/08 Procedure for Corrective Action
9. PTL /QSP/09 Procedure for Preventive Action
10. PTL /QSP/10 Procedure for Control of Records
11. PTL /QSP/11 Procedure for Internal Audit
12. PTL /QSP/12 Procedure for Management Review
13. PTL /QSP/13 Procedure for Training
14. PTL /QSP/14 Procedure for Housekeeping
15. PTL /QSP/15 Procedure for Estimation of Uncertainty of measurement
16. PTL /QSP/16 Procedure for Equipment
17. PTL /QSP/17 Procedure for Measurement Traceability and Calibration
18. PTL /QSP/18 Procedure for Sampling
19. PTL /QSP/19 Procedure for Handling of Test and Calibration Items
20. PTL /QSP/20 Procedure for Assuring the Quality of Test
21. PTL /QSP/21 Procedure for Reporting of Results
22. PTL/QSP/22 Procedure for use of NABL Symbol
-----------------------------------------------------------------------------------------------------------
Note: Replace DTL with PTL for Drug Testing Laboratory.
0 comments:
Post a Comment